| SOLON Energy GmbH |
Corporate Headquarters, Berlin Adlershof |
| Area: |
36,000 sq. m site area, offices approx. 8,300 sq. m, production approx. 18,900 sq. m |
| Construction costs: |
approx. 47 million € |
| Planning period: |
2006 to 2007 |
| Foundation stone laid: |
July 12, 2007 |
| Completion: |
2008 |
| Capacity: |
The administrative and production buildings provide space for over 600 staff. |
| CO2-Savings: |
app. 600,000 up to 1,000,000 kg/a |
| Energy requirements: |
Reduction of energy consumption to around one quarter of the values of similarly sized office buildings with the same usage. |
| Building-integrated photovoltaic system: |
210 KWp |
| Architect: |
SFA Schulte-Frohlinde Architekten, Berlin |
| Energy strategy, building services engineering und construction physics: |
EGS Plan, Stuttgart |